After the equipment arrives in Kyrgyzstan, the project will move into the on-site implementation stage.
The next work will include equipment positioning, pipeline and cable coordination, electrical connections, control-system integration, fountain testing, and commissioning.
Huaxin Fountain will continue to provide installation guidance and technical support while coordinating with the local construction team. This coordination will help ensure that the lighting, audio, and control systems are installed and integrated according to the approved project design.
The final fountain performance will be adjusted during programming and commissioning after the equipment and supporting systems have been installed.